A data centre belonging to Hounslow Borough Council has been refurbished with next generation technology and infrastructure, but interestingly the rebuild was carried out in a live environment, i.e. the data centre was still operational.
The in-situ refurbishment of Hounslow Borough Council’s data centre was carried out by Comms Room Services, a British company that specialises in the design and build, refurbishment and relocation of data centres, server rooms and computer rooms.
The makeover of the old data centre included the replacement of old partition walls with a secure fire-rated structure. In addition, the raised floor was replaced and new structured cabling installed. However, the refurbishment also called for more drastic changes at the back-end of the data centre.
Its power infrastructure (i.e the UPS or uninterruptible power supply, as well as the power generator) were upgraded, as was the air conditioning systems. Both power and cooling systems made use of N+1 solutions for added redundancy and guaranteed uptime. Meanwhile the building itself also got a green gas fire suppression system, and for security purposes, the access control and CCTV system was replaced and upgraded.
The data centre also now has added safety protocols, in that in the event of fire, the environmental monitoring systems are designed to initiate a controlled shutdown and send situation updates to key staff via text alerts.
“We were very impressed with the professional conduct and performance of the Comms Room Services team,” said Andrew Grogan, Infrastructure and Networks Manager at Hounslow Borough Council. “The project was delivered to time and budget. We now have a modern, safe and operationally reliable server room.”
“Refurbishing data centres is something we do quite often and is something we have specialised in,” said Mark Allingham, managing director of Comms Room Services. “There are many historical reasons why organisations opt to refurbish their facility (instead of building a new site), such as adequate power to the site, established communication links, and the fact that people still want direct and immediate access to their hardware.”
“I believe that Hounslow Borough Council had a report done looking at the benefits of a new building, going down the cohosting route, or even selecting a greenfield site, but the report found that the best scenario was to refurbish their existing facility whilst still live,” Allingham said, speaking to eWEEK Europe.
“There has been fairly consistent demand over the years for the refurbishing of existing facilities,” he explained. “A lot of data centres we come across are older than ten years, many for example are the remains of a mainframe-based data centre, which often has ancient air conditioning systems etc.”
Allingham said that Comms Room Services has just started another data centre refurbishment for Gwynedd Council in North Wales. “In this case, we have taken the complete side of the building off and rebricked it, in order to take advantage of free air cooling, which should reduce Gwynedd Council’s power cost to run air conditioning systems by 50 percent.”
Suspended prison sentence for Craig Wright for “flagrant breach” of court order, after his false…
Cash-strapped south American country agrees to sell or discontinue its national Bitcoin wallet after signing…
Google's change will allow advertisers to track customers' digital “fingerprints”, but UK data protection watchdog…
Welcome to Silicon In Focus Podcast: Tech in 2025! Join Steven Webb, UK Chief Technology…
European Commission publishes preliminary instructions to Apple on how to open up iOS to rivals,…
San Francisco jury finds Nima Momeni guilty of second-degree murder of Cash App founder Bob…
View Comments
the data center of today needs data cabinets that are flexible enough to handle changes in device installations while still allowing for ease of cabling and maintenance,